History of the "Orzegów" coking plant

part 8

next

 

The historical path

 

 

January of 1945 is indicated by the attempts to save the coke plant from self-elimination due to the cease of coke production. Activities concerning the supply of coke plant and boiler plant with coal resulted in gunfire from Russian forces and death of workers at the coal depot. The state of the Firing Section was bad, but only residual production and restoration works were still performed. Only the battery no. 3 and undamaged chambers from batteries 1 and 2 were fully operated. The battery no. 1 was refurbished in 1946.

 

 

 

   

 

Refurbishment of coke battery in 1946

(from the collection of JSW KOKS Zabrze)

 

 

 

Manual breakdown of coke pushed out from coke battery(from the collection of JSW KOKS Zabrze)

 

   

 

 

previous

next

 

 


Projekty dofinansowane ze środków zewnętrznych